Building Update 9

Building Update 9

July 31, 2021

Building update!

Work on site has continued to progress well as we head into the peak summer weeks.

In the Boathouse, the terrace has been constructed and coated in the waterproofing membrane in advance of the decking installation. In addition, the exposed stone wall is nearly complete and the bar top has arrived on site ready for installation!

On the main site, the groundworks have commenced for the rainwater harvesting system that will allow us to sustainably meet the house’s water demand throughout the year.

Thank you as always to our builders @lilburnelliottconstruction and all subcontractors for their continued hard work.

Top
No items found.