Westcombe Build Timeline
Planning for the redevelopment of Westcombe and the Boathouse initially began in 2015 when we approached Stephen Guard of Stephen Guard Architects.
The planning application was submitted in March 2017, however given the property's prominent location in Batson creek, it took nearly 3 years to receive approval on the redevelopment.
Finally, in December 2019 we were granted planning permission for the new property. However, due to the conditions placed on the planning permission it would be another 8 months until we were finally able to commence with the demolition phase of the project.
In November 2020, demolition finally commenced on the old property. Given the large amount of asbestos cladding on the property we engaged specialists Gilpin Demolition to carry out the demolition. In just 4 weeks the team was able to safely remove and dispose of the asbestos before demolishing the old property to the ground.
.jpeg)
Whilst the demolition of our ancestors' home was met with a touch of sadness given the love they had for it, we are delighted to finally be able to commence with the construction of the new property, and hopefully make them proud.

In February, the ground works commenced on the main house and the scaffold was erected on the Boathouse.

In March, worked started on rebuilding the Boathouse

In April, work began on pouring the foundations for the house.

In May, work commenced on constructing both the internal and external walls of the house.

In June, the structural steels for the boathouse were installed and work continued on the construction of the walls of the house.

Later in June, work progressed on constructing the second floor of the Boathouse.
